Tuesday, September 3, 2013

Status of Different Blocks in the 14th Venture




BLOCK                                 COMPLETED UPTO


A                                             4th Floor

B                                             4th Floor

C                                             4th Floor

D                                            5th Floor

J                                            5th Floor

H                                           4th Floor

E, F, G & I                             Work will be started soon